Work is in full swing for last one month. I have been traveling (Domestic & International) for couple of weeks and hence the time looked very short. Made sure to visit the site every week-end, and discussed progress of work with Architect and Engineer. By mid-November, the foundation work & pillar work in progress. Around first week of December the steel rods were rooted from the pits. Temporary electric connection was taken and the submersible-motor for borewell got fixed. By third week of December, the stone work along the boundary and compound wall was done. The water-sump is coming up in the front area (near stair-case). This Saturday the concrete mixture for the same was poured in to the structure of steel rods.